Modular façade installation continues at the HIGH LIFE skyscraper development

In January, the installation of façades continued in the first-stage buildings of premium residential estate HIGH LIFE. In building, works are being carried out on the 10th floor, in building 2 and 3 on the 9th and 10th floors, respectively. Internal engineering systems of the residential part are being installed, and the sewage system is nearing completion. Preparation for installation of lift equipment is underway.

In the underground car park the finishing of such technical rooms as electric switchboards and ventilation chambers has been completed. Installation of high-voltage distribution and transformer substations has been completed and preparations for voltage supply are underway.

A total of 550 people are involved in the construction.