Preparations are being made for the installation of façade modules on the HIGH LIFE site

In July, the monolithic framing of all the buildings of the first stage was completed on the construction site of HIGH LIFE. The works on the erection of the monolith of the Feel, Heart and Soul towers are fully satisfied. The installation of engineering equipment, wall and partition walls is in progress inside the buildings.

Façade system brackets are being installed. Modules with bay windows have already been put into production, and the first samples have been delivered to the site. Preparations for installation are underway.