Progress on the construction site of HIGH LIFE Letnikovskaya, 11, continued at full speed in November.
The general contractor ANTTEQ set a high pace of construction. By early December, in Building 1, monolithic works were in progress on the fifth floor, in Building 2 – on the eighth floor and in Building 3 – on the seventh floor.
In the underground parking, the laying of walls and partition walls are in the final stage. The roofing of the single-storey extensions is being waterproofed.
The builders have started laying the external utility and stormwater sewage networks and continue laying the heating system.
Soon, future residents will be able to see what the geometric facades of the skyscrapers will look like in reality: in December, they plan to start assembling a life-size model of the building’s future facade.