In September, waterproofing inspections were completed on the roofs of the three towers in the HIGH LIFE skyscraper complex. The buildings in the first phase have been successfully connected to the city’s power supply system. Hydraulic tests of the heating plant were completed, and preparations are underway to activate the heating system.
The preparatory stage of landscaping both the inner courtyard and the outer perimeter is nearing completion.
The installation of decorative panels on the building facades is progressing actively. Glazing of the storefronts on the ground floors, where cafes, restaurants, and boutiques will eventually be located, has also begun.